RES Playground Remodel - GOCO

Tentative Volunteer Work Schedule

Week

Activity

Volunteers needed?

work to be done

JUNE 1 - 7

Demolition and Construction mobilization

4

removing basketball hoops and straw bales

JUNE 8 - 14

Excavation/grading and boulder staging

2 - 4

removing posts, flagging, boulder placement, demo tie walls, moving wood chips

JUNE 10th, 6pm

VOLUNTEER ORIENTATION

all

register for TBR and discuss volunteer tasks for the coming weeks. RES Library

JUNE 15 - 21

Boulder placement, posts, start entrance

2 - 4

sweeping boulders, simple concrete work

JUNE 22 - 28

grade path, install climbing wall

4

raking DG, installing climbing panels, raking wood chips

JUNE 29 - JULY 2

install entrance, slide, zip

4

raking wood chips, concrete work

JULY 6 - 12

finish active zone element instillations

4

raking wood chips, clean up

JULY 13 - 19

pre-school fencing

10

fence building, raking wood chips

JULY 20 - 26

Chain link fence building

4

chain link fence building

JULY 27 - AUG 2

DG path instillation

4

flagging, raking

AUG 3 - 9

Soccer field construction, landscaping

4

raking gravel, planting trees, shrubs

AUG 9 - 16

Fairy garden construction

10

fairy garden stage construction and planting

AUG 17 - 23

soft opening and changes

10

test run everything

AUG 24 - 30

clean up and planning for opening

6

clean up, install signs, finishing touches, advertise

AUG 31st

OPENING CEREMONY

10

event prep and coordination

We recieved news April 9th that the Ridgway Elementary School Playground renovation project was selected for funding!  Construction will start this summer on Phase I of the renovations.  

icon Full GOCO Application (53.85 MB)

Ridgway Elementary School is embarking on an exciting project to revamp the current playground.  We need your input and help!

Donations are tax-deductible and 100% goes directly to the playground project.

The master plan for the Playground Renovation Project from CCCD is completed and is exciting.